Kavach 4.0 on 2,633 route km; with the older version, Kavach is installed on about 6% of India's rail network
The automatic train protection system nearly doubled its version 4.0 coverage between March and July 2026. The Railways plan 9,000 route km more in two years; ₹3,875 crore has been spent so far.








Official recordKavach version 4.0 had been commissioned on 2,633 route km as on 31 July 2026, Railway Minister Ashwini Vaishnaw said in a written answer in the Rajya Sabha on 7 August 2026 (Unstarred Question 2374, para 9): 1,423 route km on the Delhi–Mumbai route and 1,210 on Delhi–Howrah. Kavach is an indigenously developed automatic train protection system that applies the brakes if a loco pilot fails to keep within speed limits.
Official recordEarlier official totals for version 4.0: 1,452 route km (Lok Sabha reply, 11 March 2026), 1,638 (Ministry release, 26 March 2026) and 2,490 as on 13 July 2026 (Ministry release, 22 July 2026).
Verified factThe older version 3.2 runs on 1,465 route km of South Central Railway. Adding the two, as the Ministry itself did on 26 March (1,638 + 1,465 = 3,103 route km "installed"), Kavach is installed on 4,098 route km. Indian Railways' network was 69.44 thousand route km on 31 March 2025 (Economic Survey 2025-26, Statistical Table 1.26), so Kavach covers about 6% of it; version 4.0 alone covers about 4%. On 23 September 2026 the Ministry reported upgrading 108 route km of version 3.2, between Malkajgiri and Kamareddi, to version 4.0; that changes the version split, not the total.
Official recordTrackside Kavach work has been taken up on 21,794 route km covering the Golden Quadrilateral, Golden Diagonal, high-density network and identified sections (para 10). Kavach is fitted on 6,290 locomotives, with work under way on 7,190 more and on 1,200 EMU/MEMU trains (paras 11–12).
Official recordPlan: on 26 March 2026 the Ministry said it planned "to expand Kavach network by 9,000 Route Km in next two years and thereafter it is expected to grow upto 10,000 Route Km per year" (PIB Release ID 2245720).
Verified factPace so far: version 4.0 went from 1,638 route km on 26 March to 2,633 on 31 July 2026, 995 route km in 127 days, or about 2,860 a year at that rate. The two-year plan implies about 4,500 a year. Commissioning comes section by section, so the pace is uneven.
Official recordMoney: ₹3,875 crore had been spent on Kavach works up to June 2026, and ₹2,066 crore is allocated for 2026-27 (para 13); up to February 2026 the figure was ₹2,763.90 crore. Trackside and station equipment costs about ₹50 lakh a km and locomotive equipment about ₹80 lakh a locomotive (Lok Sabha reply, 11 March 2026).
Official recordThe wider safety record: consequential train accidents fell from 135 in 2014-15 to 16 in 2025-26, and there were 2 in 2026-27 up to June, according to the Ministry, which attributes the decline to "various safety measures taken over the years". Deaths in such accidents: 18 in 2024-25, 17 in 2025-26. Year by year: 107 (2015-16), 104, 73, 59, 55, 22 and 35 (Covid years 2020-21 and 2021-22), 48, 40 and 31 (2024-25). Safety-related spending rose from ₹39,200 crore in 2013-14 to ₹1,17,693 crore in 2025-26.
CommentaryThe Minister's characterisation, in the same answer: "Kavach work is going at good pace in the entire country. Requisite funds are made available as per the progress of works." The question had asked for "the percentage of passenger trains and kilometre route currently equipped"; the answer gave route km and no percentage.
Official recordWhat is not in the record: the Ministry has not published a completion date for the whole network, and the latest official total we found is for 31 July 2026. We found no recent statement on Kavach's pace from opposition parties in primary form. What to watch: the next official route-km total, and progress against the 9,000 route km plan.
The proof.
The route-km sections in the Rajya Sabha answer add up to 2,633 (1,423 + 1,210); the Ministry's own March total (1,638 + 1,465 = 3,103) uses the same method as our 4,098; the yearly accident figures for 2014-15 to 2023-24 add up to the Ministry's decade total of 678.
- Rajya Sabha, Unstarred Question 2374, answered 07.08.2026 (PDF)
- Ministry of Railways, Lok Sabha reply on Kavach, 11.03.2026 (PIB Release ID 2238425)
- Ministry of Railways, Railway Minister reviews Kavach progress, 26.03.2026 (PIB Release ID 2245720)
- Ministry of Railways, rail safety and Kavach, 22.07.2026 (PIB Release ID 2287638)
- Ministry of Railways, KAVACH 4.0 on South Central Railway, 23.09.2026 (PIB Release ID 2313758)
- Ministry of Railways, consequential accidents 2014-15 to 2023-24 (graph), 27.11.2024 (PIB Release ID 2078100)
- Ministry of Railways, safety record, 08.08.2025 (PIB Release ID 2154316)
- Economic Survey 2025-26, Statistical Appendix Table 1.26 (PDF)