Thiruparankundram Deepam: what the Madras High Court ordered, and where the state's appeal stands
The High Court directed that the Karthigai Deepam be lit at a stone pillar on the hill from 2025 onwards. Tamil Nadu has appealed; the Supreme Court has not stayed the order and is to hear the matter on 17 November. Hindu organisations are protesting for its implementation.







Official recordOn 1 December 2025, the Madurai Bench of the Madras High Court (Justice G.R. Swaminathan) allowed four writ petitions and directed "the temple management/devasthanam to light the Karthigai Deepam at Deepathoon also apart from the usual places", adding: "The Karthigai Deepam shall be lit from this year onwards at Deepathoon also" (W.P.(MD) No. 32317 of 2025 etc., para 42). The Deepathoon is a stone pillar on Thiruparankundram hill in Madurai; the court recorded that it is 50 metres from the Sikandar Badusha dargah (para 36) and held that lighting the lamp there would not affect the rights of the dargah or of Muslims (para 41).
Official recordOn 3 December 2025, the day of the festival, the lamp was lit at the Uchi Pillaiyar temple at 6 pm but not at the pillar. The judge held that his order had been breached and permitted the petitioner and ten others to light the lamp under CISF protection (Cont.P.(MD) No. 3594 of 2025, paras 2, 3 and 13).
Official recordOn 6 January 2026, a Division Bench (Dr Justice G. Jayachandran and Justice K.K. Ramakrishnan) disposed of 20 writ appeals with two directions: the Devasthanam "must light the lamp at the Deepathoon", subject to conditions the Archaeological Survey of India sets to protect the monuments on the hill; and the Devasthanam's team is to light it during the Karthigai Deepam festival, with "No public" allowed to accompany it and the District Collector co-ordinating and supervising (W.A.(MD) No. 3188 of 2025 etc., para 141). The bench held that the pillar stands on the part of the hill a civil court declared to be temple property, and that the Tamil Nadu Waqf Board, which argued that the pillar belongs to the dargah, had no locus (para 140(e)). It called the district administration's fear of a breach of peace "nothing but an imaginary ghost" (para 140(j)).
ReportedTamil Nadu's TVK government, which took office in May 2026, filed a special leave petition in the Supreme Court on 11 June. On 3 August, a bench of Justices Aravind Kumar and Vipul M. Pancholi issued notice but did not stay the High Court's order, and tagged the appeal with a pending petition by the Hindu Dharma Parishad; that petition is listed for 17 November. We have not yet seen the Supreme Court's order.
ReportedOn 22 June, the state told the High Court that it could not immediately implement the order because appeals were pending in the Supreme Court.
AllegationThe state's case: in an affidavit in the Supreme Court reported on 13 November, the Hindu Religious and Charitable Endowments (HR&CE) department, which administers the temple, said the festival lamp has been lit for more than 150 years at the Deepa Mandapam near the Uchipillaiyar temple, not at the hilltop or at the stone pillar now described as the Deepathoon, and relied on the High Court's 1996 directions in W.P. No. 18884 of 1994.
CommentaryHindu organisations, including the Hindu Munnani and the VHP, are demanding that the state implement the High Court's order. We found no public statement from the dargah management for this report; the dargah is among the parties to the Supreme Court proceedings.
UnverifiedA report on 14 November said police detained a VHP functionary in Chengalpattu district and that the Hindu Munnani has called a protest for 18 November. We could not find a police statement or a second source, and have not named him.
UnverifiedA Division Bench is reported to have stayed the contempt proceedings against officials on 18 March 2026; we have seen only one report of this.
The proof.
The High Court's directions are quoted from the orders themselves, with page and paragraph, and rechecked by script. The Supreme Court's position and the state's affidavit are labelled as reported until the documents are in hand; the detention rests on a single report and is marked unverified.
- Madras High Court (Madurai Bench), W.P.(MD) No. 32317 of 2025 etc., order of 01.12.2025 (PDF)
- Madras High Court (Madurai Bench), W.A.(MD) No. 3188 of 2025 etc., judgment of 06.01.2026 (PDF)
- LawBeat, 3 Aug 2026: Supreme Court issues notice, declines stay
- Deccan Herald, 3 Aug 2026: Supreme Court issues notice
- The Federal, 13 Nov 2026: HR&CE affidavit in the Supreme Court
- The News Minute: Tamil Nadu moves Supreme Court; High Court hearing of 22 June
- Organiser, 14 Nov 2026: detention report (single source)