Nitish Setu opens in Bihar nearly six years after the December 2020 completion date in its loan plan
The Prime Minister dedicated the six-lane Kacchi Dargah–Bidupur bridge over the Ganga on 21 November. The project's own reports to the Asian Development Bank show how far it slipped: 58% of the contract's work was done by June 2023, when the original programme had it finished.








Official recordPrime Minister Narendra Modi on 21 November 2026 dedicated the six-lane Dargah–Bidupur cable bridge over the Ganga, named Nitish Setu in honour of former Chief Minister Nitish Kumar, at a programme in Vaishali where projects worth around Rs 34,470 crore were inaugurated or begun, according to the Press Information Bureau (PIB).
Official recordPIB's release of 20 November says the extradosed cable-stayed bridge was built at a cost of around Rs 4,280 crore, and that the 19.7 km project connects Kachhi Dargah on NH-22 in Patna district with Bidupur on NH-322 in Vaishali district, with a 9.7 km main bridge and 10 km of approach roads.
Official recordThe bridge was built for the Bihar State Road Development Corporation (BSRDCL), a Government of Bihar undertaking, by a joint venture of Daewoo E&C and Larsen & Toubro, under an EPC agreement signed on 10 February 2016, with an appointed date of 16 January 2017 and an original contract sum of Rs 3,115 crore (BSRDCL Environmental Monitoring Report to the ADB, April–June 2024, Table 1). The project was financed by an Asian Development Bank loan of $500 million and $215 million from the Government of Bihar, on a total estimate of $715 million in end-2015 prices (ADB Project Administration Manual, June 2016, Table 1 and p.30).
Official recordThe Full Picture. The ADB's Project Administration Manual of June 2016 lists, among the key milestones, "1.4 Construction works completed by December 2020" (p.29, Design and Monitoring Framework). It set an output of 9.8 km of road bridge structure built "By 2020".
Official recordBy June 2023, work worth Rs 1,804.23 crore, or 57.92% of the Rs 3,115 crore contract, had been done. The original work programme had 100% done by then; the revised programme, 63.76% (BSRDCL Environmental Monitoring Report, April–June 2023, Table 5, p.15).
Official recordBy June 2024, physical progress was 73.89% and financial progress 70.90%, and the scheduled completion date was 31 December 2024 (BSRDCL Environmental Monitoring Report, April–June 2024, Table 5, p.15, and Table 1, p.5).
ReportedA 4.57 km stretch from Kacchi Dargah to Raghopur was opened on 23 June 2025 by then Chief Minister Nitish Kumar (Swarajya, 23 June 2025; PatnaPress, July 2026). In April 2025, a report said the project, "originally scheduled for completion in July", had faced delays due to the previous year's flooding; the then Road Construction Minister, Nitin Nabin, said it would be completed by the year-end (Swarajya, 22 April 2025, citing the Times of India).
ReportedIn July 2026, a cost of Rs 4,988.40 crore, including land acquisition, was reported and attributed to the state government, with about Rs 3,000 crore said to come from the ADB loan and about Rs 2,000 crore from the state (PatnaPress). This differs from PIB's figure of around Rs 4,280 crore. Neither source says what its figure includes, and we could not reconcile them.
CommentaryAt Vaishali, the Prime Minister said of the bridge: "The youth here will have easier access to education, and the elderly to healthcare" (PIB, 21 November).
CommentaryRJD leader Tejashwi Yadav criticised naming the bridge after a living leader and alleged that the BJP-led NDA government was trying to signal that Nitish Kumar was "politically finished" (Daily Jagran, 21 November). Independent MP Pappu Yadav said on 22 November: "If you have so much respect for Nitish Kumar, then I urge you to make Nishant Kumar the chief minister" (ANI).
Verified factWhat is not known: we found no official account from the Bihar government or BSRDCL of why the December 2020 target moved to 31 December 2024 and then slipped again, and no official statement of the final cost and what it includes. The ADB's project completion report has not been published. The monitoring reports do not say what share of the delay was due to floods, river changes or other causes.
The proof.
The 2020 milestone, the cost estimate and the financing plan are read from the ADB's 2016 Project Administration Manual. The contract dates, the June 2023 and June 2024 progress figures and the 31 December 2024 scheduled completion date come from BSRDCL's own monitoring reports to the ADB; our script recomputes the percentages from the rupee figures. The opening and the Rs 4,280 crore cost are from PIB. The 2025 partial opening, the July 2026 cost figure and the April 2025 explanation of the delay are reported, not official records we hold.
- PIB (PMO): PM to visit Bihar on 21 November, 20 Nov 2026
- PIB (PMO): PM in Vaishali, Bihar, 21 Nov 2026
- ADB: Project Administration Manual, Bihar New Ganga Bridge Project, June 2016 (PDF)
- BSRDCL: Environmental Monitoring Report, April–June 2023 (PDF, via ADB)
- BSRDCL: Environmental Monitoring Report, April–June 2024 (PDF, via ADB)
- Swarajya, 22 Apr 2025: bridge nears completion
- Swarajya, 23 Jun 2025: Kacchi Dargah–Raghopur stretch opened
- PatnaPress, Jul 2026: cost and funding
- Daily Jagran, 21 Nov 2026: inauguration and naming row
- ANI, 22 Nov 2026: Pappu Yadav on the naming